Assembly of full-scale IPM systems is underway

During the last couple of weeks, the work of assembling the full-scale IPM systems has been undertaken. The IPM system comes with two different protrusion lengths, and the longer systems have a mass of more than 300 kg. On Friday the 17th of March, one of the systems were tested for the first time. During week 12, the plan is to assemble and test all four systems.